EnBi in JV with SIEMENS AUSTRIA unite to successfully deliver Lot 1: SCADA Project for OSHEE Group
January 2024 | Posted by EnBi Power
Starting Point
In the framework of the Albanian Goverment Energy Action to diversify energy production sources, Voltalia won the auction for 140 MW Plant.
EnBi was chosen through tender process due to its technical presentation and quality of the products and solutions offered.
Customer Benefits
- High quality work performed and high quality products. ( lower maintenance costs)
- Very good implementation time. (earlier start of production and energy sales)
140 MW
15.05.2022 – 06.11.2023
Our Solution Approach
- Efficient technical solutions;
- Siemens products in protection, control and monitoring and SCADA, MV switchgears.
- Close cooperation with the long time partners to delivery an optimal project.
- Sustainable solutions such as bird diverters in the whole length of OHL.
- Acceleration plan to optimize completion time.
Quote about the Project
Project of Firsts:
- First project in PV and cooperation with a new partner Voltalia;
- First 220 kV cable line in Albania;
- First time that Bird Diverters are implemented in Albania;
- First time in Albania where 19.2km of 220 kV OHL are implemented in only 5 months;
- First time 220kV hot-deep-galvanized tower designed, developed and tested by EnBi Power.
220/30 kV SS
19km OHL 220 kV
220 kV Cable Line & OHL Bay in existing Fier SS